Whether it can confirm which Scottish islands it plans to connect to a subsea fibre cable, as part of the R100 programme, and whether it anticipates this being completed on schedule.

Started with S6W-03099 on 15 Sep 2021; latest 1 Dec 2022. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
442 days
15 Sep 2021 to 1 Dec 2022
Answered
2 of 2
by Kate Forbes, Ivan McKee
Asked by
1
Donald Cameron

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-03099 15 Sep 2021 Donald Cameron Con Answered

    To ask the Scottish Government whether it can confirm which Scottish islands it plans to connect to a subsea fibre cable, as part of the R100 programme, and whether it anticipates this being completed on schedule.

    Kate Forbes, 28 Sep 2021: As part of the Reaching 100% (R100) North lot contract, 16 subsea cables will be delivered to 15 Scottish islands - Colonsay, Iona and Lismore in the Argyll & Bute local authority area; Eigg in the Highland local authority area; Eday, Flotta, Hoy, Rousay, Sanday, Shapinsay and Stronsay in the Orkney Islands local auth…
  2. S6W-12864 1 Dec 2022 Donald Cameron Con Answered

    Whether it will provide an update on whether the subsea cables to (a) Colonsay, (b) Iona, (c) Lismore, (d) Eigg, (e) Eday, (f) Flotta, (g) Hoy, (h) Rousay, (i) Sanday, (j) Shapinsay, (k) Stronsay, (l) Fair Isle, (m) Unst, (n) Whalsey and (o) Yell will be laid by the end of 2022.

    Ivan McKee, 14 Dec 2022: All of the 16 new R100 subsea cables connecting 15 Scottish islands - Colonsay, Iona, Lismore, Eigg, Eday, Flotta, Hoy, Rousay, Sanday, Shapinsay, Stronsay, Fair Isle, Unst, Whalsey and Yell – were laid during Summer 2022. Planned post-laying activity is now continuing with work to establish terrestrial connections on…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads