Whether it will provide an update on (a) how much of the reported £200 million for rail improvement works as part of the Aberdeen City Region Deal to reduce journey times between Aberdeen and the central belt has been s…

Started with S6W-01498 on 14 Jul 2021; latest 20 Sep 2021. Each later question says it follows up an earlier answer.

Follow-ups
4
longest chain 2 steps
Span
68 days
14 Jul 2021 to 20 Sep 2021
Answered
5 of 5
by Graeme Dey
Asked by
1
Liam Kerr

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S6W-01498 14 Jul 2021 Liam Kerr Con Answered

    To ask the Scottish Government whether it will provide an update on (a) how much of the reported £200 million for rail improvement works as part of the Aberdeen City Region Deal to reduce journey times between Aberdeen and the central belt has been spent, (b) what it has been spent on, (c) how much of any remaining funds it plans to spend on the railway between Aberdeen and Dundee, and (d) what time saving has been …

    Graeme Dey, 6 Aug 2021: By way of an update against the progress of the Aberdeen to Central belt rail project:- (a) £1.68 million has been spent on this project to date. (b) This funding has been used i) to identify the signalling and infrastructure interventions that enable the required capacity enhancements and journey time savings, and ii…
  2. S6W-02143 9 Aug 2021 Liam Kerr Con Answered

    Whether it will provide the information that was requested regarding how much of any remaining funds it plans to spend on the railway between Aberdeen and Dundee and, if this information is not held centrally at present, whether it will confirm if there is an option that none of the funding could be allocated to that route.

    Graeme Dey, 6 Sep 2021: Transport Scotland will be in a position to confirm details in Spring 2022, once the option selection phase for the project is completed and the estimated costs and benefits have been determined against each option. Currently there is no option being considered which does not see the allocated funding being spent on t…
  3. S6W-02148 9 Aug 2021 Liam Kerr Con Answered follows S6W-01498

    Whether its response at (b)(ii) means that it no longer plans to meet the commitment, as part of the Aberdeen City Region Deal, to reduce journey times between Aberdeen and the central belt by 20 minutes, or whether the "maximum benefits" referred to are anticipated to at least meet that commitment, and, if it is still committed to reducing journey times between Aberdeen and the central belt by 20 minutes, when it p…

    Graeme Dey, 6 Sep 2021: Transport Scotland remains committed to working with key industry partners to achieve, by 2026, the 20 minutes journey time saving between Aberdeen and Edinburgh (average journey time of 2 hours 10 minutes for express services). This outcome was agreed at the final meeting of the Aberdeen to Central Belt Reference Gro…
  4. S6W-02565 25 Aug 2021 Liam Kerr Con Answered follows S6W-01498

    Whether it will provide a detailed plan for how the £198.32 million, that remains from the £200 million, will be spent to reduce journey times between Aberdeen and the central belt, and in which financial year(s) it will be spent.

    Graeme Dey, 13 Sep 2021: Network Rail is currently assessing the options identified for delivering the required capacity enhancements and journey time savings between Aberdeen and the central belt. When the most effective options have been selected in alignment with available funding, it will then be possible to compile a detailed plan for de…
  5. S6W-03197 20 Sep 2021 Liam Kerr Con Answered

     what information it has regarding when Network Rail will conclude its assessment of the options identified; who will select the most effective options; what the criteria are for this selection; when this selection will be made, and how long it will take "to compile a detailed plan for delivering the project".

    Graeme Dey, 4 Oct 2021: The options selection work will be concluded by Transport Scotland, Network Rail and ScotRail by summer 2022. In accordance with the Rail Enhancements Capital Investment Strategy each of the options will be appraised to identify which offer the most benefits and also represent value for money. Network Rail recently co…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads