Parliament Workbench

Question thread · 2 questions

When it plans to commence physical groundwork on the Laurencekirk junction.

Started with S5W-25045 on 29 Aug 2019; latest 24 Sep 2019. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
26 days
29 Aug 2019 to 24 Sep 2019
Answered
2 of 2
by Michael Matheson
Asked by
1
Liam Kerr

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S5W-25045 29 Aug 2019 Liam Kerr Con Answered

    To ask the Scottish Government when it plans to commence physical groundwork on the Laurencekirk junction.

    Michael Matheson, 23 Sep 2019: The Scottish Government is committed to completing the A90/A937 Laurencekirk Junction Improvement for the people of the north east as soon as possible. We are currently taking forward the detailed development and assessment of the preferred option with a view to publishing draft Orders later this year for comment. Del…
  2. S5W-25469 24 Sep 2019 Liam Kerr Con Answered

    By what date it will bring forward the relevant statutory procedures for the improvement scheme.

    Michael Matheson, 1 Oct 2019: As confirmed in my reply to question S5W-25045 , w e are currently taking forward the detailed development and assessment of the preferred option with a view to publishing draft Orders later this year for comment.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads