What implications the situation at the construction company, Carillion, might have on the completion of the Aberdeen Western Peripheral Route and other infrastructure projects throughout Scotland.
Started with S5T-00865 on 15 Jan 2018; latest 7 Jun 2018. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Government what implications the situation at the construction company, Carillion, might have on the completion of the Aberdeen Western Peripheral Route and other infrastructure projects throughout Scotland.
Oral · 16 Jan 2018 -
(Official Report, c. 3), what contracts (a) it, (b) its agencies and (c) the Scottish Futures Trust has or has had with Carillion, broken down by (i) the value of the contract, (ii) the date the contract was signed and (iii) the date the contract was or is expected to be completed.
Keith Brown, 31 Jan 2018: a) The Scottish Government does not have any contracts direct with Carillion. b) The following table lists contracts between Carillion and SG agencies taken from the Public Contract Scotland (PCS) system. These records go back to start of PCS in 2008: Contract Name Contracting Authority Award Date End Date Estimated V… -
(Official Report, c. 3), in light of the collapse of Carillion, what steps it is taking to assess the financial health of its other private contractors.
Keith Brown, 31 Jan 2018: Public bodies may select suppliers to be invited to bid based upon a number of criteria. One such criterion is that public bodies may set requirements relating to economic and financial standing designed to determine if the potential bidder has the necessary economic and financial capacity to perform the contract. Dec… -
(Official Report, c. 3), in light of the collapse of Carillion, whether it will confirm what contingency plans it has to deal with the collapse of any of its other major private building contractors, and whether it now plans to revisit these.
Keith Brown, 31 Jan 2018: As part of on-going Contract Management of all its major contracts, the Scottish Government monitors the financial health of its contractors. Due to the varying size and complexity of the contracts involved, the type and level of assessment is undertaken on a contract by contract basis and is proportionate and relevan… -
(Official Report, c. 3), in light of the collapse of Carillion, how it monitors the debts of its private contractors, and what level of debt would constitute "a concern".
Keith Brown, 31 Jan 2018: As part of on-going Contract Management of all its major contracts the Scottish Government monitors the financial health of its contractors. Due to the varying size and complexity of the contracts there is not a specific level of debt which would constitute a concern. The type and level of assessment is undertaken on … -
(Official Report, c. 3), in light of the collapse of Carillion, whether it will provide a list of all companies that it has live contracts with whose current balance sheet debt it considers to be "a concern".
Keith Brown, 31 Jan 2018: It would be inappropriate for the Scottish Government to publish a list of contractors where debt levels were a concern, as this could be deemed market sensitive. -
(Official Report, c. 3), in light of the collapse of Carillion, what consideration it gives to the state of a private contractor's pension fund when considering awarding a contract.
Keith Brown, 31 Jan 2018: The regulation of pensions is a reserved matter and the issues raised by the Carillion situation are likely to be governed by those regulations. Nonetheless public bodies may select suppliers to be invited to bid based upon a number of criteria. One such criterion is that public bodies may set requirements relating to… -
On how many occasions it has sought Parent Group Guarantees from a private contractor after the (a) tendering process and (b) signing of the contract in instances where there has been concerns regarding a company's financial health.
Keith Brown, 5 Mar 2018: We are able to provide information on contracts awarded after March 2016 when the Scottish Government introduced a single contracts database for contracts worth more than £50,000. Gathering information on contracts awarded prior to this date could only be obtained at disproportionate cost as it would require the searc… -
How many of its current contractors are subject to Parent Company Guarantees, and how much these represent as a percentage of the total (a) number of contractors and (b) value of contracted work.
Keith Brown, 5 Mar 2018: We are able to provide information on contracts awarded after March 2016 when the Scottish Government introduced a single contracts database for contracts worth more than £50,000. Gathering information on contracts awarded prior to this date could only be obtained at disproportionate cost as it would require the searc… -
Whether it will confirm which of the projects listed were affected by the liquidation of Carillion, also broken down by the financial impact of this (a) to each project overall and (b) on the public purse.
Keith Brown, 21 Jun 2018: The UK Official Receiver is still in the process of liquidating Carillion and so the final impact on the public purse is not yet available.
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.