How its plans are progressing to build a national film studio.

Started with S4O-04688 on 28 Sep 2015; latest 15 Feb 2016. Each later question says it follows up an earlier answer.

Follow-ups
4
longest chain 1 step
Span
140 days
28 Sep 2015 to 15 Feb 2016
Answered
4 of 5
by Fiona Hyslop
Asked by
2
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4O-04688 28 Sep 2015 George Adam SNP Oral

    To ask the Scottish Government how its plans are progressing to build a national film studio.

    Oral · 8 Oct 2015
  2. S4W-29954 15 Feb 2016 Liam McArthur LD Answered

    (Official Report, c. 2), whether the proposal from the private sector developer to build a film studio is still being considered by the film studio delivery group and, if so, what progress is being made with it.

    Fiona Hyslop, 14 Mar 2016: As I set out in my recent evidence to the Economy, Energy and Tourism Committee, progress is being made. The Film Studio Delivery Group (FSDG) is continuing to work with the private sector developer, announced on 9 March 2016 as Wardpark Studios Ltd at Cumbernauld. A planning application is about to be submitted to ex…
  3. S4W-29955 15 Feb 2016 Liam McArthur LD Answered follows S4O-04688

    (Official Report, c. 2), whether any additional bids have been submitted for the development of a film studio.

    Fiona Hyslop, 14 Mar 2016: The Film Studio Delivery Group (FSDG) welcomes proactive approaches from private sector developers and will assess each proposition in terms of value for the screen sector, value for money, whether the proposition meets the requirements of legal and financial due diligence and whether the proposition would be financia…
  4. S4W-29956 15 Feb 2016 Liam McArthur LD Answered follows S4O-04688

    (Official Report, c. 2), whether the film studio delivery group has assessed any sites for potential development.

    Fiona Hyslop, 14 Mar 2016: The Film Studio Delivery Group procured EKOS in 2014 to undertake a feasibility study and options appraisal for a film studio which included a significant number of sites for potential development. This study was refreshed in December 2015. Wardpark at Cumbernauld has been assessed and their intention to expand was an…
  5. S4W-29957 15 Feb 2016 Liam McArthur LD Answered follows S4O-04688

    (Official Report, c. 2), what recent discussions it has had with Creative Scotland and Scottish Enterprise regarding the development of a film studio.

    Fiona Hyslop, 14 Mar 2016: The Film Studio Delivery Group (FSDG) consists of representatives from the Scottish Government, Creative Scotland and Scottish Enterprise. The FSDG meets on a fortnightly basis to discuss progress, actions, and any new potential opportunities for the development of a film studio. The last meeting took place on 1 March…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads