What the lay-up costs were of the MV Coruisk for the 2012-13 winter period.

Started with S4W-20841 on 24 Apr 2014; latest 16 May 2014. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
22 days
24 Apr 2014 to 16 May 2014
Answered
2 of 2
by Keith Brown
Asked by
1
Jamie McGrigor

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-20841 24 Apr 2014 Jamie McGrigor Con Answered

    To ask the Scottish Government what the lay-up costs were of the MV Coruisk for the 2012-13 winter period.

    Keith Brown, 9 May 2014: The lay-up costs for the MV Coruisk for the 2012-13 winter period, December 2012 to March 2013, were £379,000.
  2. S4W-21212 16 May 2014 Jamie McGrigor Con Answered

    What the lay-up costs of the craft were in 2013-14, and what the reason is for any difference with the 2012-13 figure.

    Keith Brown, 2 Jun 2014: The MV Coruisk was not in lay-up in 2013-14 as it was operating on the Wemyss Bay-Rothesay route prior to moving to Gourock-Dunoon and therefore incurred no lay-up costs.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads