What the (a) start and (b) completion dates are for the electrification of the East Kilbride railway line.

Started with S4W-18953 on 16 Dec 2013; latest 1 May 2014. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
136 days
16 Dec 2013 to 1 May 2014
Answered
2 of 2
by Keith Brown
Asked by
1
Margaret McCulloch

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-18953 16 Dec 2013 Margaret McCulloch Lab Answered

    To ask the Scottish Government what the (a) start and (b) completion dates are for the electrification of the East Kilbride railway line.

    Keith Brown, 6 Jan 2014: No dates have been determined yet for the electrification of the East Kilbride railway line.
  2. S4W-20963 1 May 2014 Margaret McCulloch Lab Answered

    When it expects to determine the dates for the electrification of the East Kilbride railway line.

    Keith Brown, 12 May 2014: The Scottish Government, along with industry, is developing its rail electrification strategy to determine future phases of electrification. As yet, there is no publication date.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads