Question thread · 2 questions

When it will make its recommendation on the Rosyth International Container Terminal project.

Started with S4W-08312 on 26 Jun 2012; latest 5 Sep 2012. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
71 days
26 Jun 2012 to 5 Sep 2012
Answered
2 of 2
by Keith Brown
Asked by
1
Helen Eadie

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S4W-08312 26 Jun 2012 Helen Eadie Lab Answered

    To ask the Scottish Executive when it will make its recommendation on the Rosyth International Container Terminal project.

    Keith Brown, 19 Jul 2012: Ministers will consider the report of the public local inquiry and determine whether or not to make the order as soon as possible thereafter.
  2. S4W-09413 5 Sep 2012 Helen Eadie Lab Answered

    Whether it will ensure that the competitive position of the proposed Rosyth international container terminal will not be adversely impacted by the time taken to consider the inquiry report and the determination of the harbour revision order.

    Keith Brown, 12 Sep 2012: We will consider the report of the inquiry, which is now expected by the end of October, and determine the harbour revision order application as quickly as possible.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.