What the £44 million TrakCare contract will cover in NHS (a) Ayrshire and Arran, (b) Borders, (c) Grampian, (d) Greater Glasgow and Clyde and (e) Lanarkshire and whether the cost of TrakCare in Lothian will also be cove…
Started with S3W-34514 on 15 Jun 2010; latest 21 May 2015. Each later question says it follows up an earlier answer.
Follow-ups
2
Span
1,801 days
Answered
3 of 3
Asked by
1
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive what the £44 million TrakCare contract will cover in NHS (a) Ayrshire and Arran, (b) Borders, (c) Grampian, (d) Greater Glasgow and Clyde and (e) Lanarkshire and whether the cost of TrakCare in Lothian will also be covered.
Nicola Sturgeon, 23 Jun 2010: This covers individual licence costs, and deployment and support charges for the five participant boards for a 10 year period. The costs for TrakCare in Lothian Health Board are not included. -
What role it had in the procurement of the TrakCare contract for each of the NHS boards.
Shona Robison, 3 Jun 2015: The Personal Medical Services (PMS) contract was negotiated on behalf of a consortium of NHS boards. There were two main governance boards. A consortium management group chaired by the Chief Executive of NHS Greater Glasgow and Clyde with membership drawn from senior managers from all of the consortium boards. The boa… -
What (a) role it had in the procurement of and (b) guidance it issued regarding the TrakCare contract for NHS (i) Lothian, (ii) Grampian, (iii) Highland, (iv) Orkney and (v) Shetland.
Shona Robison, 3 Jun 2015: NHS Lothian had procured the Personal Medical Services (PMS) Trakcare system prior to the announcement of the contract with the consortium boards referenced in S3W-34514. NHS Grampian were one of the five consortium boards in that procurement. NHS Highland and NHS Shetland have procured and implemented the Trakcare PM…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.