To ask the Scottish Executive what the procurement process is for the new Southern General Hospital.
Nicola Sturgeon, 24 Nov 2009: NHS Greater Glasgow and Clyde is the procuring authority. The board''s procurement strategy utilised the competitive dialogue procedure to facilitate discussion with bidders around pre-determined technical and commercial matters. The outcome of the competitive dialogue is the selection of a preferred partner who will … -
Who will be liable if the costs of the new Southern General Hospital contract are exceeded.
Nicola Sturgeon, 4 Dec 2009: I refer the member to the answers to question S3W-29188, on 2 December 2009. All answers to written parliamentary questions are available on the Parliament''s website, the search facility for which can be found at http://www.scottish.parliament.uk/Apps2/Business/PQA/default.aspx.
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.