Question thread · 3 questions
What the total cost to date is of the Aberdeen Western Peripheral Route, including the cost of the public consultation.
Started with S3W-28645 on 4 Nov 2009; latest 19 Nov 2009. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive what the total cost to date is of the Aberdeen Western Peripheral Route, including the cost of the public consultation.
Stewart Stevenson, 16 Nov 2009: The cost of preparatory work undertaken, up to the end of October 2009, is approximately £91 million. Similar to other trunk road projects, this has included scheme development, environmental impact assessment, consultation with statutory and non-statutory bodies, publication of statutory documentation, topographical … -
Whether it will indicate the cost of (a) scheme development, (b) environmental impact assessments, (c) consultations with statutory and non-statutory bodies, (d) publication of statutory documentation, (e) topographical surveys, (f) ground investigation works, (g) land purchase payments and (h) compensation payments.
Stewart Stevenson, 9 Dec 2009: The total scheme development costs for work undertaken is approximately £34 million. The following costs are included as part of the total scheme development costs but can be identified separately: Environmental Impact Assessment - £8.1 million, Topographical Surveys - £0.7 million, Ground Investigation Works (includi… -
Further to the answers to question S3W-28285 and S3W-28645 by Stewart Stevenson on 12 and 16 November 2009 respectively, whether the estimated £91 million cost of preparatory work for the Aberdeen Western Peripheral Route includes (a) the estimated £51 million for relocation of the International School of Aberdeen to Pitfodels and (b) VAT.
Stewart Stevenson, 9 Dec 2009: Expenditure up to the end of October 2009, in relation to the relocation of the International School of Aberdeen, is included in the total cost of preparatory work of approximately £91 million undertaken up to the end of October 2009. This includes VAT paid up to the end of October 2009, in relation to the relocation …
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.