What the total cost to date is of the Aberdeen Western Peripheral Route, including the cost of the public consultation.

Started with S3W-28645 on 4 Nov 2009; latest 19 Nov 2009. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 1 step
Span
15 days
4 Nov 2009 to 19 Nov 2009
Answered
3 of 3
by Stewart Stevenson
Asked by
2
MSPs

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S3W-28645 4 Nov 2009 Alex Johnstone Con Answered

    To ask the Scottish Executive what the total cost to date is of the Aberdeen Western Peripheral Route, including the cost of the public consultation.

    Stewart Stevenson, 16 Nov 2009: The cost of preparatory work undertaken, up to the end of October 2009, is approximately £91 million. Similar to other trunk road projects, this has included scheme development, environmental impact assessment, consultation with statutory and non-statutory bodies, publication of statutory documentation, topographical …
  2. S3W-29178 19 Nov 2009 Lewis Macdonald Lab Answered

    Whether it will indicate the cost of (a) scheme development, (b) environmental impact assessments, (c) consultations with statutory and non-statutory bodies, (d) publication of statutory documentation, (e) topographical surveys, (f) ground investigation works, (g) land purchase payments and (h) compensation payments.

    Stewart Stevenson, 9 Dec 2009: The total scheme development costs for work undertaken is approximately £34 million. The following costs are included as part of the total scheme development costs but can be identified separately: Environmental Impact Assessment - £8.1 million, Topographical Surveys - £0.7 million, Ground Investigation Works (includi…
  3. S3W-29187 19 Nov 2009 Lewis Macdonald Lab Answered follows S3W-28645 also cites S3W-28285

    Further to the answers to question S3W-28285 and S3W-28645 by Stewart Stevenson on 12 and 16 November 2009 respectively, whether the estimated £91 million cost of preparatory work for the Aberdeen Western Peripheral Route includes (a) the estimated £51 million for relocation of the International School of Aberdeen to Pitfodels and (b) VAT.

    Stewart Stevenson, 9 Dec 2009: Expenditure up to the end of October 2009, in relation to the relocation of the International School of Aberdeen, is included in the total cost of preparatory work of approximately £91 million undertaken up to the end of October 2009. This includes VAT paid up to the end of October 2009, in relation to the relocation …

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads