Question thread · 2 questions
How much it will contribute to the costs of the Fastlink project in Glasgow.
Started with S3W-27502 on 18 Sep 2009; latest 12 Feb 2010. Each later question says it follows up an earlier answer.
Follow-ups
1
Span
147 days
Answered
2 of 2
Asked by
2
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive how much it will contribute to the costs of the Fastlink project in Glasgow.
Stewart Stevenson, 25 Sep 2009: I have asked my officials to discuss further with Glasgow City Council officials a Scottish Government financial contribution to an initial phase of the Fastlink initiative. -
How much money it has allocated to the Fastlink initiative.
Stewart Stevenson , 8 Mar 2010: Scottish Ministers have previously indicated they are willing to contribute to an initial phase for Fastlink/Bus Rapid Transit (BRT) which will provide improved connections between the City Centre, the SECC and the new Southern General Hospital. Strathclyde Partnership for Transport and Glasgow City Council are now fi…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.