What proportion of the £15 million allocated to the Home Insulation Scheme will be spent on (a) insulation materials, (b) labour costs to install insulation, (c) publicity and promotion and (d) administration.

Started with S3W-23529 on 5 May 2009; latest 22 Dec 2010. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 2 steps
Span
596 days
5 May 2009 to 22 Dec 2010
Answered
3 of 3
by Alex Neil
Asked by
1
Patrick Harvie

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S3W-23529 5 May 2009 Patrick Harvie Green Answered

    To ask the Scottish Executive what proportion of the £15 million allocated to the Home Insulation Scheme will be spent on (a) insulation materials, (b) labour costs to install insulation, (c) publicity and promotion and (d) administration.

    Alex Neil, 11 May 2009: Aspects of the Home Insulation Scheme are still under development and it is therefore not possible to finalise such a breakdown at this stage.
  2. S3W-27369 16 Sep 2009 Patrick Harvie Green Answered

    What proportion of the £15 million allocated to the Home Insulation Scheme will be spent on (a) insulation materials, (b) labour costs to install insulation, (c) publicity and promotion and (d) administration.

    Alex Neil, 24 Sep 2009: It is estimated that the cost of the development, implementation, administration and marketing, including publicity and promotion, of the Home Insulation Scheme, by the managing agent for the scheme, the Energy Saving Trust, will be approximately £5.5 million. This funding will provide for a combination of direct deli…
  3. S3W-38534 22 Dec 2010 Patrick Harvie Green Answered

    What proportion of the £15 million allocated to the Home Insulation Scheme in its first year was spent on (a) insulation materials, (b) labour costs to install insulation, (c) publicity and promotion and (d) administration.

    Alex Neil, 25 Jan 2011: The breakdown is as follows : Percentage of Home Insulation Scheme (HIS) 2009-10 Budget Allocated Category | A/B - insulation materials/labour1 | 35% C “ publicity and promotion | 3% D “ administration2 | 7% Notes: 1. Information is not collected on the breakdown between labour and materials costs. Includes enabling f…

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads