Parliament Workbench

Question thread · 2 questions

When it expects to have an orthoptist pre-school screening programme in every NHS board area.

Started with S3W-22474 on 30 Mar 2009; latest 1 Oct 2009. Each later question says it follows up an earlier answer.

Follow-ups
1
longest chain 1 step
Span
185 days
30 Mar 2009 to 1 Oct 2009
Answered
2 of 2
by Shona Robison
Asked by
1
Rhoda Grant

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S3W-22474 30 Mar 2009 Rhoda Grant Lab Answered

    To ask the Scottish Executive when it expects to have an orthoptist pre-school screening programme in every NHS board area.

    Shona Robison, 27 Apr 2009: A date has not been specified. The NHS boards who have not yet introduced an orthoptist pre-school screening programme are working towards doing so, or towards introducing a programme supervised by an orthoptist or an optometrist.
  2. S3W-27937 1 Oct 2009 Rhoda Grant Lab Answered

    What the timescale is for every NHS board area to have an orthoptist pre-school screening programme in.

    Shona Robison, 28 Oct 2009: As stated in my previous answer, a date has not been specified. The NHS boards who have not yet introduced an orthoptist pre-school screening programme are working towards doing so, or towards introducing a programme supervised by an orthoptist or an optometrist. The Scottish Government Health Directorates will issue …

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.

All question threads