Question thread · 2 questions
How many consented renewable energy projects in the north of Scotland are currently awaiting connection to the grid.
Started with S3O-04712 on 6 Nov 2008; latest 11 Nov 2008. Each later question says it follows up an earlier answer.
Follow-ups
1
Span
5 days
Answered
2 of 2
Asked by
1
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive how many consented renewable energy projects in the north of Scotland are currently awaiting connection to the grid.
Jim Mather, 6 Nov 2008: There are 13 consented renewable energy projects awaiting connection to the grid in the north of Scotland, with a total capacity of 451 megawatts. -
Whether it will list the (a) 13 consented renewable energy projects in the north of Scotland awaiting connection to the grid and (b) dates on which consents were granted.
Jim Mather, 19 Nov 2008: A list of the (a) 13 consented renewable energy projects in the north of Scotland awaiting connection to the grid and (b) dates on which consents were granted, are given in the following table. (a) Renewable Energy Project | Capacity (MW) | (b) Date of Consent A''Chruach, | 50 | May 2008 Ark Hill, | 12 | Awaiting cons…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.