To ask the Scottish Executive what progress is being made on the Aberdeen Crossrail project.
Tavish Scott, 10 Mar 2006: In line with our PartnershipAgreement Commitment, we continue to support the development of feasibility workfor the Aberdeen Crossrail scheme. The proposal is being led by NESTRANS who areresponsible for ensuring delivery of the completed feasibility work by end 2006. Transport Scotland Officialscontinue to work close… -
Whether it anticipates that Network Rail's new infrastructure investment plans will impact on the completion date for the Aberdeen Crossrail project.
Tavish Scott, 4 May 2006: The proposals for the AberdeenCrossrail scheme are still at feasibility stage. The decision on implementationand delivery of this scheme will be dependant firstly on successful completion ofSTAG2 and then subject to the outcome of the Strategic Projects Review and futureSpending Reviews. The Network Rail fund is forpe…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.