Question thread · 4 questions
When it anticipates the settlement date will be for the cost of repairs to the Erskine Bridge following the damage inflicted by an offshore structure.
Started with S2W-13787 on 25 Jan 2005; latest 4 Oct 2006. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive when it anticipates the settlement date will be for the cost of repairs to the Erskine Bridge following the damage inflicted by an offshore structure.
Nicol Stephen, 8 Feb 2005: A debate on the parties’ pleadings will take place on 27 to 30 September 2005. The issue of liability and quantum of damages will be determined by the court if the parties are unable to reach agreement on these issues. It would, of course, be possible for the parties to reach an out of court settlement and the Scottis… -
What further progress has been made in the pursuit of the cost of repairs to the Erskine Bridge following the damage caused by an offshore structure colliding with the bridge.
Tavish Scott, 25 Jan 2006: Our legal advisers have successfully secured an abandonment of the debate which was due to take place on 27 to 30 September 2005 and secured an award of expenses in our favour. They are currently pressing the court and other parties to confirm a final hearing on the issue of liability and quantum of damages, which wil… -
What method of dispute resolution has been chosen in relation to the recovery of the costs incurred on the repairs of the damage caused to the Erskine Bridge by an offshore structure.
Tavish Scott, 25 Oct 2006: Since January 2006 the otherparties involved in the action have declined to discuss any form of resolution of the matter and the Executive is pursuing its legal action against the parties responsiblefor the damage to the Erskine Bridge. A legal hearing to determine liability and the amountof damages has been fixed to … -
When an outcome is likely to be achieved anent the dispute over the payment of the cost of repairs to the Erskine Bridge.
Tavish Scott, 25 Oct 2006: I refer the member to the answer to question S2W-28903 on 25 October 2006. Allanswers to written parliamentary questions are available on the Parliament’s website,the search facility for which can be found at http://www.scottish.parliament.uk/webapp/wa.search. Transport Scotland hasoperational responsibility for this …
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.