Question thread · 3 questions
Whether work on the M77 (Malletsheugh to Fenwick) will be allowed to commence prior to the resolution of all outstanding issues surrounding the Glasgow South Orbital Road and, if not, why this decision has been made and…
Started with S1W-03204 on 10 Dec 1999; latest 25 Aug 2000. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive whether work on the M77 (Malletsheugh to Fenwick) will be allowed to commence prior to the resolution of all outstanding issues surrounding the Glasgow South Orbital Road and, if not, why this decision has been made and what the implications for the proposed M77 Extension of the Glasgow South Orbital Road not proceeding would be.
Sarah Boyack, 12 Jan 2000: Scottish Executive officials have already met officials of East Renfrewshire and South Lanarkshire Councils, the promoters of the Glasgow Southern Orbital (GSO), to discuss co-ordination of the M77 (Malletsheugh to Fenwick) and the GSO. One key objective will be to ensure a safe linkage between the two new roads. On t… -
Whether any progress has been made in discussing co-ordination of the M77 and the Glasgow Southern Orbital; whether the Scottish Executive intends to progress the two roads through a joint single contract, or how otherwise it intends to secure the co-ordination of the M77 and the Glasgow Southern Orbital.
Sarah Boyack, 21 Aug 2000: Objections were made to the planning applications, compulsory purchase orders, and side road orders needed by East Renfrewshire and South Lanarkshire Councils for the construction of the Glasgow Southern Orbital. These objections require to be considered at a public local inquiry into the proposals. It is expected tha… -
Whether it is satisfied that the timescale for all possible planning and legal procedures in connection with the Glasgow Southern Orbital is such that procurement of it and the M77 through a single Public/Private Partnership will entail no delays in the projected timescale for completion of the A77/M77 upgrade.
Sarah Boyack, 15 Sep 2000: I refer to my answer to question S1W-8805 on 21 August 2000. A single Public/Private Partnership contract for the M77 and the Glasgow Southern Orbital could only proceed if East Renfrewshire Council and South Lanarkshire Council are able to complete the statutory procedures for the Glasgow Southern Orbital. The curren…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.