Parliament Workbench

Question thread · 3 questions

When it will report on its consideration of a priority dispatch system for the Scottish Ambulance Service.

Started with S1O-03531 on 29 May 2001; latest 6 Nov 2001. Each later question says it follows up an earlier answer.

Follow-ups
2
longest chain 2 steps
Span
161 days
29 May 2001 to 6 Nov 2001
Answered
3 of 3
by Susan Deacon
Asked by
1
Pauline McNeill

The thread, in order

Each answer’s opening lines; open a question for the full text
  1. S1O-03531 29 May 2001 Pauline McNeill Lab Answered

    To ask the Scottish Executive when it will report on its consideration of a priority dispatch system for the Scottish Ambulance Service.

    Susan Deacon, 6 Jun 2001: Health Department officials are currently discussing the costs and benefits of priority-based ambulance dispatch with the Scottish Ambulance Service. Once these discussions are complete, the Executive will decide whether the Ambulance Service should go ahead to prepare a full business case.
  2. S1W-16820 5 Jul 2001 Pauline McNeill Lab Answered

    When Health Department officials will report on their discussions regarding priority-based ambulance dispatch and whether it will undertake further consultation based on the outcome of the discussions.

    Susan Deacon, 26 Oct 2001: It is for the Scottish Ambulance Service to consult on proposals for operational changes. I understand that the service, in preparing the case for priority based dispatch, has consulted widely within NHSScotland, including clinicians, patients and patient representatives. The Scottish Executive has now asked the servi…
  3. S1W-19707 6 Nov 2001 Pauline McNeill Lab Answered

    Whether a timetable has been set for the Scottish Ambulance Service to develop a business case including proposals for the implementation of priority-based dispatch.

    Susan Deacon, 20 Nov 2001: I understand from the Scottish Ambulance Service that the board is scheduled to consider the full business case for priority-based dispatch at the beginning of 2002. The Executive expects to receive the full business case following that meeting, and will reach a final decision as soon as possible thereafter.

How this thread is put together

Follow-up
A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
Several citations
When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
Thread
Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.