Question thread · 3 questions
Whether it will create enterprise zones in Scotland and, if so, what process it will undertake in deciding which areas to designate enterprise zones; which areas it will designate; what the timetable is, and what outcom…
Started with S4W-00647 on 8 Jun 2011; latest 13 Mar 2012. Each later question says it follows up an earlier answer.
The thread, in order
Each answer’s opening lines; open a question for the full text-
To ask the Scottish Executive whether it will create enterprise zones in Scotland and, if so, what process it will undertake in deciding which areas to designate enterprise zones; which areas it will designate; what the timetable is, and what outcomes it hopes to achieve in the (a) short and (b) long term.
Fergus Ewing, 23 Jun 2011: The Scottish Government is committed to the establishment of enterprise zones in Scotland and to maximising their economic impact. However, we are still in the early stages of determining the appropriate assessment criteria on which to base our detailed decision making. We expect to reach an initial view on this by ea… -
When it will reach a decision on the appropriate assessment criteria on which to base the detailed decision making on how best to establish enterprise zones.
Fergus Ewing, 15 Nov 2011: The criteria have been agreed with ministers and the assessment of individual sites is currently being progressed. The assessment criteria will be published in the near future when Ministers make decisions on Scotland’s Enterprise Areas. -
And S4W-03808 by Fergus Ewing on 15 November 2011, what (a) criteria it used in and (b) the conclusions were of its environmental impact assessment of potential enterprise areas.
Derek Mackay, 26 Mar 2012: “Environmental impact assessment” generally refers to the assessment of the environmental effects of projects and is undertaken in support of planning and consenting processes. Any development progressed at the sites selected as Enterprise Areas will be subject to project-level screening under the relevant environment…
How this thread is put together
- Follow-up
- A question whose text says it is “further to the answer to question …” (or reply, response, or asks for a “substantive answer” to an earlier question). The question it names is its parent.
- Several citations
- When a question cites more than one earlier question, the most recent one we hold is used as the parent; the others are listed as “also cites”.
- Thread
- Follow parents back to the first question; every question that leads back to it is in this thread. Branches are shown in date order.