What assessment it has made of the minimum carbon capture rate that would be considered acceptable in order for the proposed Peterhead gas-…

Answered Asked by Mark Ruskell Green Lodged 29 Oct 2026

The question

To ask the Scottish Government what assessment it has made of the minimum carbon capture rate that would be considered acceptable in order for the proposed Peterhead gas-fired power plant to operate following its development.

The answer

Answered by Ivan McKee on 6 Nov 2026 · 8 days after it was lodged, on time

It would not be appropriate to comment further about a decision on a section 36 application made under the Electricity Act 1989 once it has been issued.The full reasoning for the decision is publicly available online at the Energy Consents Unit portal: https://www.energyconsents.scot/ApplicationDetails.aspx?cr=ECU00003433.

In the Official Report