Written Question · S7W-04466 · Session 7

Whether all infrastructure required to connect the Kilmarnock South Battery Energy Storage System to the transmission network was assessed …

Answered Asked by Carol Mochan Lab Lodged 23 Oct 2026

The question

To ask the Scottish Government whether all infrastructure required to connect the Kilmarnock South Battery Energy Storage System to the transmission network was assessed during the original consenting process and, if not, what additional infrastructure has subsequently been identified and for what purpose.

The answer

Answered by Ivan McKee on 6 Nov 2026 · 14 days after it was lodged, on time

All matters considered and the reasons for the decision dated 10 March 2023 to grant s36 consent for Kilmarnock South BESS are contained in the decision letter, and it would not be appropriate to add to its terms.The decision letter is available to view online at the Energy Consents Unit portal: https://www.energyconsents.scot/ApplicationDetails.aspx?cr=ECU00003435.

In the Official Report

No contribution in the Official Report cites S7W-04466 by reference.