On what date the decision was taken to replace the additional £40 million ScotZEB2 funding with ScotZEB3, which minister authorised that de…

Answered Asked by Stephen Kerr Con Lodged 8 Oct 2026

The question

To ask the Scottish Government on what date the decision was taken to replace the additional £40 million ScotZEB2 funding with ScotZEB3, which minister authorised that decision, and what reasons were recorded for doing so.

The answer

Answered by Stephen Flynn on 23 Oct 2026 · 15 days after it was lodged, on time

The decision to develop options for a third competitive phase of ScotZEB (ScotZEB3) was taken by the former Cabinet Secretary for Transport on 16 October 2025. ScotZEB3 was developed as the swiftest and most certain route to provide a further £45 million of support for the decarbonisation of Scotland's bus sector.