Whether it has assessed any potential impact of the construction of hyperscale artificial intelligence data centres on housing construction…

Answered Asked by Carol Mochan Lab Lodged 30 Sep 2026

The question

To ask the Scottish Government whether it has assessed any potential impact of the construction of hyperscale artificial intelligence data centres on housing construction and housing delivery, including whether demand for skilled labour, construction materials, land, energy infrastructure and any related resources could affect the timescales or costs of residential housebuilding projects across Scotland.

The answer

Answered by Hannah Mary Goodlad on 28 Oct 2026 · 28 days after it was lodged, on time

The notification direction we issued during the summer enables strategic oversight and monitoring of data centre applications over 50MW power capacity, including the overall impacts and implications for wider infrastructure.