Written Question · S7W-03590 · Session 7
How much of the £41.7 million grant funding that it announced on 23 July 2024 for the purpose of delivering 252 new zero-emission buses and…
The question
To ask the Scottish Government how much of the £41.7 million grant funding that it announced on 23 July 2024 for the purpose of delivering 252 new zero-emission buses and coaches was spent, and whether any additional funding was requested by any of the eight operators that received the funding.
The answer
A total of £41,649,182.68 was spent through Phase 2 of the Scottish Zero Emission Bus Challenge Fund (ScotZEB2) supporting delivery of 263 zero-emission buses and coaches. No additional funding was requested by participating operators.With every £1 of public funding leveraging in £3 of private investment, ScotZEB2 has successfully demonstrated how collaboration between operators, manufacturers, energy providers and financiers can accelerate the transition to zero-emission public transport across Scotland.
In the Official Report
No contribution in the Official Report cites S7W-03590 by reference.