What estimate it has made of the economic impact on Motherwell, Cambuslang and the wider Lanarkshire supply chain should the Dalzell plate …

Answered Asked by Paul Sweeney Lab Lodged 16 Sep 2026

The question

To ask the Scottish Government what estimate it has made of the economic impact on Motherwell, Cambuslang and the wider Lanarkshire supply chain should the Dalzell plate mill close permanently.

The answer

Answered by Stephen Flynn on 29 Sep 2026 · 13 days after it was lodged, on time

This government is committed to maintaining Scotland's domestic steel capacity and fully appreciates the economic importance of Dalzell to the local area. The priority of the Scottish Government is to see the plant operational.

In the Official Report

No contribution in the Official Report cites S7W-03346 by reference.