Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S7W-03008 · Session 7

When it expects to complete the verification process for Future Farm Investment Scheme claims.

Answered Asked by Finlay Carson Con Lodged 7 Sep 2026

The question

To ask the Scottish Government when it expects to complete the verification process for Future Farm Investment Scheme claims.

The answer

Answered by Jim Fairlie on 22 Sep 2026 · 15 days after it was lodged, on time

Scottish Government Rural Payments and Inspections Division are processing received applications in a timely and robust manner to ensure the safeguarding of public funds. The deadline for submitting evidence is 30 September 2026. As of 15 September 2026, 423 beneficiaries are still to provide evidence that the funded investment was carried out.

In the Official Report

No contribution in the Official Report cites S7W-03008 by reference.