Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S7W-02660 · Session 7

How many actions contained in its Offshore Wind Skills Programme (a) have been completed, (b) remain outstanding and (c) have had their del…

Answered Asked by Liam Kerr Con Lodged 24 Aug 2026

The question

To ask the Scottish Government how many actions contained in its Offshore Wind Skills Programme (a) have been completed, (b) remain outstanding and (c) have had their delivery date revised.

The answer

Answered by Stephen Gethins on 7 Sep 2026 · 14 days after it was lodged, on time

The Offshore Wind Skills Priorities & Action Plan was developed with industry and key public sector partners and sets out 12 initial actions over the next two years. The plan is jointly owned by partners
- public bodies, education providers and sector skills organisations
- who have committed to taking these actions forward.Five actions in the Offshore Wind Skills Priorities & Action Plan have been completed, and seven actions are underway. Six of these actions are on track to be completed by, or ahead of, their respective delivery dates. The Offshore Wind Skills Programme Board approved revisions to the delivery dates of three actions, two of which have been completed, with the third on track for delivery.The Scottish Government and delivery partners remain committed to implementing the Offshore Wind Skills Priorities & Action Plan in full.

In the Official Report

No contribution in the Official Report cites S7W-02660 by reference.