The question
To ask the Scottish Government what steps CalMac is taking to ensure that planned and ongoing maintenance on MV Hallaig does not result in a permanent reduction in Raasay’s scheduled lifeline ferry service.
The answer
As part of the new CHFS3 contract, CalMac is introducing an increased programme of regular maintenance across the network. This is intended to improve reliability and resilience by reducing the likelihood of breakdowns, which can cause significant disruption to island connectivity.CalMac has been working with the Raasay community, as with communities across the network, to introduce such maintenance in a way that minimises disruption.