Written Question · S7W-02093 · Session 7

What proportion of ScotWind development expenditure is currently expected to be awarded to Scottish-based manufacturing, fabrication, engin…

Answered Asked by Sanne Dijkstra-Downie LD Lodged 27 Jul 2026

The question

To ask the Scottish Government what proportion of ScotWind development expenditure is currently expected to be awarded to Scottish-based manufacturing, fabrication, engineering and construction firms and what steps it is taking to increase the participation of domestic businesses in the programme.

The answer

Answered by Stephen Gethins on 21 Aug 2026 · 25 days after it was lodged, on time

Based on the 16 projects that submitted Supply Chain Development Statements (SCDS) updates in 2026, Scotland’s share of total commitments in each category is Development 62%; Manufacturing & Fabrication 20%; Installation 36%; and Operation 70%.This information can be verified on the Crown Estate Scotland supply chain dashboard https://crownestatescotland.com/supply-chain-informationThe Scottish Government is leveraging private investment into the offshore wind supply chain and ports infrastructure through our strategic investment – to date we have unlocked almost £900m of investment into projects with the potential to support up to 5,000 jobs.Our enterprise agencies are providing targeted development support and connecting our supply chain companies with offshore wind projects and principal suppliers and contractors, enabling them to bid for
- and crucially to win
- work in renewables.Where levers are reserved, such as with the Clean Industry Bonus, the Scottish Government continues to urge the UK Government to consider all available options to bolster the expansion of domestic manufacturing, support order book certainty for suppliers, and avoid the offshoring of economic opportunities from our energy transition.

In the Official Report

No contribution in the Official Report cites S7W-02093 by reference.