Written Question · S7W-02041 · Session 7
Further to the answer to question S6W-40952 by Gillian Martin on 24 October 2025, what progress has been made in addressing the damage to t…
The question
To ask the Scottish Government, further to the answer to question S6W-40952 by Gillian Martin on 24 October 2025, what progress has been made in addressing the damage to the parallel roads of Lochaber Site of Special Scientific Interest at Achnabobane, including what measures have been taken to restore the site and prevent further damage.
The answer
Following the reported damage to the Parallel Roads of Lochaber Site of Special Scientific Interest (SSSI), a number of actions have been taken. This includes the arrest of alleged perpetrators of the damage and the preparation of a report for the procurator fiscal, and separate enforcement notice action by The Highland Council in relation to unconsented development.The damaging activities at Achanbobane have caused irreparable damage to some of the protected interest of the SSSI because the processes which created them, glacial ice and meltwater deposition, cannot be replicated. Nevertheless, NatureScot is working with The Highland Council to ensure that the limited re-instatement which is possible is carried out without further damage to the site.As a stronger deterrence to further damage to the SSSI occurring at Achnabobane, in September 2025 Scottish Ministers put in place a Nature Conservation Order. Only through the vigilance of the community, NatureScot and partners will any further damaging activity be detected and reported, allowing rapid action to be taken to stop it.
In the Official Report
No contribution in the Official Report cites S7W-02041 by reference.