What the current timeline is for finalising the Sectoral Marine Plan for Offshore Wind Energy, and what remaining steps must be completed b…

Answered Asked by Liam Kerr Con Lodged 30 Jun 2026

The question

To ask the Scottish Government what the current timeline is for finalising the Sectoral Marine Plan for Offshore Wind Energy, and what remaining steps must be completed before adoption.

The answer

Answered by Stephen Gethins on 28 Jul 2026 · 28 days after it was lodged, on time

The Updated Sectoral Marine Plan for Offshore Wind Energy is expected to be adopted in Summer 2026.Significant progress has already been made since our consultation on the draft Plan last year, including completion of the Appropriate Assessment, consultation with Statutory Nature Conservation Bodies, and ongoing work to identify compensatory measures for seabird impacts.The remaining work relates primarily to finalisation of the Plan and its associated impact assessments including Habitats Regulations Appraisal processes. These documents are currently being finalised and will be submitted for Ministerial consideration in the coming weeks. This includes consideration by UK Ministers.Subject to Ministerial approval, the Plan will be adopted and all supporting documents will be published.