Written Question · S7W-01420 · Session 7

What progress it has made towards its target of 20GW of operational onshore wind capacity by 2030, and what assessment it has made of wheth…

Answered Asked by Kristopher Leask Green Lodged 30 Jun 2026

The question

To ask the Scottish Government what progress it has made towards its target of 20GW of operational onshore wind capacity by 2030, and what assessment it has made of whether current consenting rates are sufficient to meet that target.

The answer

Answered by Stephen Gethins on 20 Jul 2026 · 20 days after it was lodged, on time

As of the end of Q1 2026, there was 10.7GW of onshore wind installed capacity with an additional 5.9GW awaiting construction and 2.1GW under construction. This gives a total of 18.7GW consented onshore wind capacity across these categories. These figures are taken from publications released by the Department of Energy Security and Net Zero (DESNZ).It is vital to note that achieving consent is only one of several factors that determine deliverability. Grid availability and a route to market through Contracts for Difference are key factors outwith the Scottish Government’s control.