Whether design work has been carried out for the electrification of the Maryhill Line.
The question
To ask the Scottish Government whether design work has been carried out for the electrification of the Maryhill Line.
The answer
The option to electrify the Maryhill Line has been previously been considered as part of wider reviews of Scotland’s railway infrastructure to identify routes that could benefit from electrification. Assessments that were previously undertaken in the 2010’s identified that the required works would require a number of overbridge reconstructions and track lowers throughout the route.While electrification of the Maryhill Line does not form part of the current rail investment programme, it remains an option for future delivery alongside a number of other potentially valuable schemes.
In the Official Report
No contribution in the Official Report cites S7W-00870 by reference.