 in light of the Audit Scotland report, Criminal Courts Backlog Follow-Up, and given its acknowledgement that previous engagement with the …

Answered Asked by Stephen Kerr Con Lodged 5 Jun 2026

The question

To ask the Scottish Government, in light of the Audit Scotland report, Criminal Courts Backlog Follow-Up, and given its acknowledgement that previous engagement with the third sector was too late to be effective, what action it is taking to ensure that third sector partners are formally involved from the outset in shaping the refreshed 2026 strategy.

The answer

Answered by Neil Gray on 16 Jun 2026 · 11 days after it was lodged, on time

We acknowledge Audit Scotland’s findings that engagement with the third sector on the Delivery Plan happened late in the process. However, engagement with stakeholders is a key part of the policy process ensuring our key stakeholders were involved in the activities that were reflected in the plan. We are working with our partners on the next version of the delivery plan and appropriate engagement with stakeholders will be considered as part of that process.

In the Official Report