How many battery energy storage applications have been (a) granted and (b) rejected by the Energy Consents Unit.
The question
To ask the Scottish Government how many battery energy storage applications have been (a) granted and (b) rejected by the Energy Consents Unit.
The answer
It is the Scottish Ministers who determine applications made under sections 36 and 37 of the Electricity Act 1989. The Energy Consents Unit administers these applications on their behalf.Details of decisions made by the Scottish Ministers about battery energy storage system (BESS) applications are as follows:Consented 62Refused 0