What its response is to reports that the opening of the new Nairn Academy campus has been delayed until September 2026, and whether it has …

Answered Asked by Tim Eagle Con Lodged 21 May 2026

The question

To ask the Scottish Government what its response is to reports that the opening of the new Nairn Academy campus has been delayed until September 2026, and whether it has held any discussions with the Highland Council regarding any potential further delays.

The answer

Answered by Mairi McAllan on 8 Jun 2026 · 18 days after it was lodged, on time

The Highland Council has confirmed that the new Nairn Academy campus will open to pupils following the October holidays in 2026. This decision was taken following a short delay to the completion of construction works and to allow sufficient time to for the Council to ensure the building is appropriately handed over, supporting a smooth transition for pupils and staff, and minimising disruption during term time.The Scottish Government and Scottish Futures Trust continue to engage with the Council, which has confirmed that no further delay to the school’s opening is anticipated.

In the Official Report

No contribution in the Official Report cites S7W-00274 by reference.