What investment it plans to make to increase the average speeds of trains on the (a) Highland Main Line and (b) Far North Line.

Answered Asked by Tim Eagle Con Lodged 21 May 2026

The question

To ask the Scottish Government what investment it plans to make to increase the average speeds of trains on the (a) Highland Main Line and (b) Far North Line.

The answer

Answered by Stephen Flynn on 3 Jun 2026 · 13 days after it was lodged, on time

In regards to a) Highland Main Line, I refer the Member to the answer to question S6W-27087 on 7 May 2026.In regards to (b) Far North Line, the Scottish Government granted authority and funding for enhancements to the Radio Electronic Token Block signalling system on the Far North Line and for line speed improvements at various points on the Line and the majority of these enhancements are now completed. In relation passing loops, I refer the Member to answer to question S6W-29458 on 17 September 2024.All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answersTransport Scotland continually revises its programme of works against priorities in the context of available funding. This ensures it can deliver the right projects at the right time as it seeks to progress its rolling programme of decarbonisation, whilst also delivering rail passenger and freight services that meet user expectations.

In the Official Report