The question

To ask the Scottish Government how many premises (a) have been connected and (b) are waiting to be connected to broadband through Project Gigabit in the Highlands and Islands region, broken down by local authority area.

The answer

Answered by Tom Arthur on 1 Jun 2026 · 13 days after it was lodged, on time

There are currently two Project Gigabit in Scotland contracts that are in their delivery phase which intersect with the Highlands and Islands Parliamentary Region – the regional contract awarded to GoFibre which covers the North East of Scotland and the nationwide contract awarded to Openreach. While there is currently a live regional procurement underway for Orkney and Shetland, until a contract is awarded, it is not possible to provide a breakdown of the premises to be connected.a) The following table provides the number of premises that have received a connection through Project Gigabit in Scotland so far in the Highlands and Island Parliamentary Region, broken down by local authority area.Local AuthorityPGIS Contract Built*Argyll and Bute219Highland0Moray0Na h-Eileanan an Iar183*This includes incidental build – premises that were not included in the contract but which the supplier has delivered while working in the area.b) The following table provides the number of premises that are in a Project Gigabit in Scotland contract and remain to be connected in the Highlands and Island Parliamentary Region, broken down by local authority area.Local AuthorityPGIS Contract Planned*Argyll and Bute11,518Highland15,398Moray9,338Na h-Eileanan an Iar8,124