Written Question · S7W-00088 · Session 7
What its position is on whether there has been adequate monitoring of the M8 viaduct in relation to the reported delays and the reason for …
The question
To ask the Scottish Government what its position is on whether there has been adequate monitoring of the M8 viaduct in relation to the reported delays and the reason for them.
The answer
Amey is ultimately responsible for undertaking the viaduct propping works, acting as both Principal Designer and Contractor, under the Network Maintenance Contract (NMC) with Transport Scotland.Transport Scotland’s Project Team manage Amey’s performance and scrutinise Amey’s programme at weekly meetings. They undertake joint risk reviews with Amey to ensure adequate allowances are made in the programme for any risks to delivery. As a result of scrutinising the programme and risks, a Quantitative Schedule Risk Analysis (QSRA) is produced by Amey. The QSRA provides probabilities for when the project will be completed, which aids planning and communications to the public.Transport Scotland also utilise the Performance Audit Group (PAG) who audit, monitor and report on the financial, technical and performance aspects of the operating companies who are contracted to manage and maintain Scotland’s trunk roads. In addition, for this project, Transport Scotland have additional support from Turner and Townsend who provide expert scrutiny of the programme and project risks.As you are aware, Transport Scotland has established a Project Board to provide additional governance and oversight of the project, who regularly receive copies of the programme, and reporting on reasons for any change at regular intervals.Finally, independent peer reviews, known as Gateway Reviews, have been undertaken at key stages of the project with the support of stakeholders and advisers. These Reviews provide additional assurance and, where required, recommend actions to ensure the project progresses successfully.I am, therefore, confident Transport Scotland have robust monitoring in place in relation to the programme, reported delays and the reasons for them.
In the Official Report
No contribution in the Official Report cites S7W-00088 by reference.