Written Question · S6W-44259 · Session 6

What steps it is taking to ensure that (a) ScotWind leases and (b) Supply Chain Development Statements (SCDS) produce stable, long-term eco…

Answered Asked by Mercedes Villalba Lab Lodged 11 Mar 2026

The question

To ask the Scottish Government what steps it is taking to ensure that (a) ScotWind leases and (b) Supply Chain Development Statements (SCDS) produce stable, long-term economic benefits for (i) workers and (ii) businesses in north east Scotland.

The answer

Answered by Gillian Martin on 25 Mar 2026 · 14 days after it was lodged, on time

The ScotWind leasing round and the Supply Chain Development Statement (SCDS) process have been carefully designed and are managed by Crown Estate Scotland (CES). The process has produced a leasing round focused on quality and deliverability of bids, and long-term supply chain investment which promises to be transformational for Scotland’s economy.We are building on the commitment of ScotWind developers to invest an average projection of £1.5 bn in Scotland per project by leveraging private investment in our supply chain through our offshore wind strategic investment. Working with our enterprise agencies, we continue to support companies in the North East and Moray
- areas that have provided energy security through oil and gas for generations
- to access opportunities emerging from offshore wind.