Written Question · S6W-43341 · Session 6
What measures it is taking to minimise the risk of delays in the consenting appeals process for critical grid infrastructure.
The question
To ask the Scottish Government what measures it is taking to minimise the risk of delays in the consenting appeals process for critical grid infrastructure.
The answer
The Scottish Government recognises the importance of timely consenting decisions in delivering transmission infrastructure for Scotland’s net zero ambitions. Working in partnership with industry and communities, we remain committed to our ambition to achieve a 52-week determination process to deliver Scotland’s energy transition.Since 2023 the Scottish Government has been working with the UK Government on its Planning and Infrastructure Act 2025, which finally received Royal Assent in December. Included in the Act are provisions that minimise the risk of delays in the consenting process, including replacing judicial reviews with statutory appeals and removing the automatic public inquiry while retaining it as an option, both of which take effect from 18 February.The Act granted other regulation-making powers to the Scottish Government, including the ability to set requirements for pre-application consultation and engagement of communities and to create a formal acceptance stage where we assess compliance before accepting applications. These powers are intended to further improve the efficiency of application processing, and we intend to consult on them later this year.
In the Official Report
No contribution in the Official Report cites S6W-43341 by reference.