Written Question · S6W-42478 · Session 6
Whether it plans to devolve consenting powers to local authorities for applications for the (a) construction, (b) extension and (c) operati…
The question
To ask the Scottish Government whether it plans to devolve consenting powers to local authorities for applications for the (a) construction, (b) extension and (c) operation of electricity generating stations with capacity in excess of 50 megawatts.
The answer
The Scottish Government has published a consultation on increasing the current threshold of 50MW for applications for onshore electricity generating stations to be considered by local authorities. All responses received will be carefully considered before any decision is made.
In the Official Report
No contribution in the Official Report cites S6W-42478 by reference.