Further to the answer to question S6W-29116 by Neil Gray on 6 September 2024, whether it will provide an update on what total cost has been…
The question
To ask the Scottish Government, further to the answer to question S6W-29116 by Neil Gray on 6 September 2024, whether it will provide an update on what total cost has been incurred to date in relation to the planned National Treatment Centre in NHS (a) Ayrshire and Arran, (b) Grampian, (c) Lanarkshire, (d) Lothian and (e) Tayside.
The answer
The cost incurred to date in relation to the planned National Treatment Centre in NHS Ayrshire and Arran, NHS Grampian, NHS Lanarkshire, NHS Lothian and NHS Tayside is as follows.BoardCost incurred to date on National Treatment CentreAyrshire & Arran£5,016,600Grampian£6,474,000Lanarkshire£268,000Lothian£12,532,000Tayside£12,468,438Total£36,759,038