The question
To ask the Scottish Government, further to the answer to question S6W-18275 by Gillian Martin on 1 June 2023, on how many occasions the organisations that were awarded funding from the Hydrogen Innovation Scheme in the 2023 round failed to complete key project milestones.
The answer
Three projects supported through the Hydrogen Innovation Scheme have requested no cost time extensions in order to fulfil their project outcomes. These requests have been granted by the Scottish Government and those projects currently remain active. The Scheme will come to a close in March 2026.