Whether it will provide an update on its consideration of the escalation status for NHS Forth Valley, under the NHS Scotland Support and In…

Answered Arranged question: government announcement Asked by Keith Brown SNP Lodged 8 Oct 2025

The question

To ask the Scottish Government whether it will provide an update on its consideration of the escalation status for NHS Forth Valley, under the NHS Scotland Support and Intervention Framework.

The answer

Answered by Neil Gray on 9 Oct 2025 · 1 day after it was lodged, on time

NHS Forth Valley had been experiencing difficulties with performance, including concerns raised by Healthcare Improvement Scotland following unannounced inspections in 2022. This led to the Board being escalated to Stage 4 of the NHS Scotland Support & Intervention Framework in November 2022 for governance, leadership and culture, bringing direct formal oversight and coordinated engagement from Scottish Government in the form of an Assurance Board.The NHS Forth Valley Assurance Board, which last met on 5 September 2024, was then satisfied that NHS Forth Valley has made considerable progress in delivering their Assurance and Improvement Plan and that the organisation was sufficiently evidencing tangible improvements across the three areas for which they were escalated: governance, leadership and culture, and the decision was taken to de-escalate the Board to Stage 3 of the Framework from 1 October 2024. Moving to Stage 3 meant that NHS Forth Valley no longer required direct formal oversight and the Assurance Board was stood down.The Board continued to be reviewed by the Scottish Government’s National Planning and Performance Oversight Group (NPPOG) and following careful consideration, the decision has been taken that NHS Forth Valley’s escalation status for governance, leadership and culture, should be lowered to Stage 2 from 9 October 2025. This decision also reflects the continued dedication, effort, and commitment of NHS Forth Valley staff which is bringing results and progress in reducing the longest waits.Scottish Government will continue to engage with NHS Forth Valley and monitor progress with a view to reporting back to NPPOG in March 2026.