To ask the Scottish Government, further to the answer to question S6W-36012 by Fiona Hyslop on 31 March 2025, by what date the construction of the controlled pedestrian crossing at Raigmore interchange in Inverness will begin.

The answer

Answered by Fiona Hyslop on 23 Sep 2025 · 8 days after it was lodged, on time

Preparatory works are progressing well with the design stage completed. The tender package was issued for pricing at the end of August 2025 and the works are currently programmed to commence on site at the start of January 2026.