Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Inspired Question · S6W-39690 · Session 6

When it will provide an update on the Berwick Bank offshore windfarm consenting application.

Answered Arranged question: government announcement Asked by Emma Harper SNP Lodged 31 Jul 2025

The question

To ask the Scottish Government when it will provide an update on the Berwick Bank offshore windfarm consenting application.

The answer

Answered by Kate Forbes on 31 Jul 2025 · 0 days after it was lodged, on time

It is not normally the case that Parliament is informed of determinations on consenting applications. However, given that Parliament is in recess and that the Berwick Bank offshore windfarm consenting application of significant interest and of strategic importance, I considered it appropriate and helpful to proactively inform Parliament of the decision made in relation to this application.I can therefore advise that Scottish Ministers have today granted consent to the application for the Berwick Bank Offshore Windfarm which will be located in the North Sea in the outer Firth of Forth. It will be one of the world’s largest windfarms and will have an estimated capacity of 4.1GW. This decision has been taken after careful and lengthy consideration of the project’s potential environmental impact and its potential impacts on other users of the sea.This decision is a major step in Scotland’s progress towards achieving net zero and tackling the climate crisis, as well as supporting national energy security and growing our green economy. Increasing renewable energy generation is critical to meeting our climate change targets, with climate change being one of the biggest threats to Scotland’s biodiversity and health of its marine ecosystems.We are requiring that the developer must deliver environmental compensation to address the environmental impacts of this windfarm, alongside measures which will mitigate and minimise impacts to other sea users. The Scottish Government will work with SSE Renewables and stakeholders on proposed environmental compensatory measures required to address the impacts of the project.Offshore wind is already one of Scotland’s greatest modern success stories – we now have the opportunity to deliver a potential offshore wind pipeline of over 40 GW putting us at the forefront of offshore wind development globally. This is the right decision for Scotland’s interests and will help to deliver significant benefits for our nation.The determination paperwork can be found here: Section 36 Consent
- Construction and Operation of Generating Station
- Berwick Bank Wind Farm
- Firth of Forth | marine.gov.scot.

In the Official Report

No contribution in the Official Report cites S6W-39690 by reference.