The question

To ask the Scottish Government, further to the answer to question S6W-32826 by Jim Fairlie on 16 January 2025, whether it will provide an update on Transport Scotland's consideration of new vessels for the Dunoon to Gourock ferry route, and when a decision will be taken.

The answer

Answered by Jim Fairlie on 24 Jun 2025 · 14 days after it was lodged, on time

A range of new vessel options for the Gourock to Dunoon and Kilcreggan ferry services are being considered within the wider Outline Business Case for investment in the routes, which also includes port infrastructure upgrades. When complete, the Outline Business Case will be reviewed by Transport Scotland Investment Decision Making Board in the first instance, currently expected to be around the end of 2025, and then presented to Ministers for decisions.