The question

To ask the Scottish Government, further to the answer to question S6W-35302 by Gillian Martin on 12 March 2025, how much it estimates would be raised in leasing fees for a 50-year lease of the site under the current ScotWind leasing process.

The answer

Answered by Gillian Martin on 14 May 2025 · 8 days after it was lodged, on time

Based on 2024 estimates, Crown Estate Scotland projects a revenue from ScotWind developments of £3.42m per gigwatt over the lifetime of the project. If leased through ScotWind then Inch Cape (1.08GW installed capacity) would return £3.7m annually.The figures provided are estimates only – actual revenues achieved will be dependent on a range of issues, including those affecting deployment scale, and timing and windspeeds.